US Highway 160 Project by MODOT

Project Facts:

  • Widen Route 160 to four lanes between I-44 in Springfield and Jackson Street in Willard

  • Resurface the existing lanes of Route 160 between I-44 in Springfield and Route AB in Willard

  • Traffic barrier wall between lanes in areas

  • Street lighting at intersections

  • Intersection improvements:

  1. J-turn at Farm Road 123/Westgate Avenue

  2. Right-in/Right-out at Haseltine Road (Farm Road 115)

  3. Roundabout at Farm Road 94 near quarry

  4. Add left-turn lane at Hughes Road

  5. Roundabout at Farm Road 103/Melville Road/Hunt Road

  6. Add a pedestrian underpass at Hunt Road

  7. Roundabout at Jackson Street

  8. REVISION - Add turn lanes at Greene County Route AB; no roundabout at this location



    Traffic Impacts:

  9. Lane closings at times on Route 160

  10. Side streets closed at times for connection into new highway lanes


Construction: Mid-summer 2019 until late 2020
Estimated total project cost: $18.6 million

Click on picture below to be directed to modot website for more information.

map route