Project improves Miller Road between W. State Highway O/Kime Street and W. New Melville Road/Farm Road 84, totaling approximately 4,070 linear feet.  Improvement includes adding a center turn lane of 14 feet in width and establishing two vehicle lanes of 12 feet in width, curbs and gutters on both sides of roadway, and a sidewalk on one side of the roadway.  Project also includes designing for and constructing a new City waterline on the east side of Miller Road between E. Jackson Street and US Route 160.  Project is expected to begin construction in early 2018.

Project Status:

Milestones

% Complete

Comments

Preliminary Design

100%

Submitted to MoDOT August 16, 2017

Right-of-Way Plans

100%

Approved by MoDOT October 5, 2017

Right-of-Way Acquisition

100%

Acquired February 21, 2019

PS&E to MoDOT

100%

MoDOT approved January 10, 2019

Bidding

100%

Estimated completion March 2019

Construction

100%

Estimated completion October 2019